PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of October 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 22, 2018 COD date. The primary critical path is through the Waste, Potable, Feedwater, and Closed Cooling Water Systems. The secondary critical path is...

PSEG Keys Energy Center LLC & SNC-Lavalin Participate In BRC Small Business Expo

PSEG Keys Energy Center LLC and SNC-Lavalin recently joined Prince George’s County Executive Rushern Baker and the Business Resource Coalition (BRC) for an afternoon of networking, and sharing of valuable resource information. The BRC offers managerial, technical and financial assistance to local businesses. Over 50 businesses participated and learned how...

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of September 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 4, 2018 COD date. The Primary Critical Path remains the completion of the STG electrical, cable pulls, terminations, commissioning 125VDC, and back feeding power...

SNC-Lavalin Construction Progress Pictures Of The PSEG Keys Energy Center LLC (8/18/17)

SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC. DCS Powered Up. East View (July 23rd). Station Battery Installation. PSEG IT Rack Installation. To view pics of our progress click here.

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of August 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018.  The Primary Critical Path runs through activities leading up to backfeed, energization of #12 Station Power Transformer and commissioning.  The STG has 10 days of float due to schedule optimization and the...

PSEG Keys Energy Center Participates In PGC SDDD’s County Connections Event

PSEG Keys Energy Center recently participated in Prince George’s County Supplier Development & Diversity Division (SDDD) County Connections event. The kickoff event was co-hosted by Council Chair Derrick Davis (District 6) and provided businesses with the opportunity to meet and receive information essential to local and regional business growth. Attendees...

SNC-Lavalin Construction Progress Pictures Of The PSEG Keys Energy Center LLC (7/15/17)

SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC. Latest Site Aerial (6/25/17). HRSG 11 Stack Topped and Silencer Support Steel Installation. Condensate Pump Motor Installation. HRSG 11 Stack Topped and Silencer Support Steel Installation. To view pics of our progress click here.

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of July 3, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 8, 2018 COD date. The STG has become the Primary Critical Path with preparations for setting of the LP Inner Casing in progress. Ready...