PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of August 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018.  The Primary Critical Path runs through activities leading up to backfeed, energization of #12 Station Power Transformer and commissioning.  The STG has 10 days of float due to schedule optimization and the...

PSEG Keys Energy Center Participates In PGC SDDD’s County Connections Event

PSEG Keys Energy Center recently participated in Prince George’s County Supplier Development & Diversity Division (SDDD) County Connections event. The kickoff event was co-hosted by Council Chair Derrick Davis (District 6) and provided businesses with the opportunity to meet and receive information essential to local and regional business growth. Attendees...

SNC-Lavalin Construction Progress Pictures Of The PSEG Keys Energy Center LLC (7/15/17)

SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC. Latest Site Aerial (6/25/17). HRSG 11 Stack Topped and Silencer Support Steel Installation. Condensate Pump Motor Installation. HRSG 11 Stack Topped and Silencer Support Steel Installation. To view pics of our progress click here.

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of July 3, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 8, 2018 COD date. The STG has become the Primary Critical Path with preparations for setting of the LP Inner Casing in progress. Ready...

SNC-Lavalin Construction Progress Pictures Of The PSEG Keys Energy Center LLC (6/23/17)

SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC. Condensate Polisher Building Steel under ACC. North Gas Yard Aerial View. Installing Control Room Floor. Elevated View ACC and HRSG12. #11 Stack Section Set.

Prince George’s County Executive Rushern Baker Meets With Students From The PSEG Keys Energy Program

Prince George’s County Executive Rushern Baker recently visited the PSEG Keys Energy Center and spoke to the 2017 graduates of the Keys Energy Program. During the visit, County Executive Baker learned about the program and spoke with students about taking advantage of the opportunity to have a potential career in...

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of June 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018.  The steam turbine generator (STG) remains the primary critical path with assembly of the low pressure turbine in progress. The plant electrical system is the next critical path with construction of the...

New: Aerial Photos Of The PSEG Keys Energy Center (Pics)

Check out the latest aerial photos of the PSEG Keys Energy Center. 

PSEG Keys Energy Center Celebrates Participant Graduation For The Keys Energy Program

Prince George's County Councilman Mel Franklin and Maryland State Delegate Susie Proctor recently joined PSEG Keys Energy Center to celebrate the graduation of the participants of the Keys Energy Program, Councilman Franklin lauded the participants for their achievements while Delegate Proctor recognized the participants with a citation.  Both officials spoke...

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of May 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018 and a target of April 1, 2018. The Steam Turbine Generator remains the primary critical path with STG Electrical the second path. Load testing of the Turbine Building Overhead Crane is scheduled...