Prince George’s County Supplier Development & Diversity Division (SDDD) in the Office of Central Services selected PSEG Keys Energy Center And SNC-Lavalin as an honoree at the “6th ANNUAL SUPPLIER DIVERSITY APPRECIATION NIGHT.”
Annually, SDDD celebrates supplier diversity and honors those who have helped us to be strategic advocates...
Dec
01
2017
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The Primary Critical Path remains the commissioning of the condensate, HRSG11, low pressure feedwater, high pressure feedwater, intermediate pressure feedwater, and fuel gas systems to support CTG 11 First Fire. ...
Nov
15
2017
In keeping with the commitments of our Community Foundation Agreement, PSEG Keys Energy Center LLC recently made it’s final $1 million payment towards the construction of a new Southern Area Aquatic and Recreation Complex (SAARC) in Brandywine, Maryland.
The last payment fulfills our $3 million commitment and donation from PSEG...
Nov
01
2017
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. PSEG Project team and Operation staff continue performing piping installation and task complete verifications to support SNC scheduling and work prioritization leading to system completions.
The Primary Critical Path remains through the Waste...
Oct
23
2017
PSEG Keys Energy Center LLC Project Compliance Officer Eben Smith recently gave a briefing to Brandywine North Keys Civic Association regarding recent updates with the project.
During the discussion, he updated the civic association members on a variety of topics ranging from SNC-Lavalin construction progress, to community benefits, to local...
Oct
16
2017
SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC.
October Aerial:
ACC Steam Distribution Manifold Painting:
CTG Air Inlet Filter Houses De-icing Section Installation:
Setting Up for HRSG-11 Hydro Test:
For more information on updates and news related to the project, click here.
Oct
02
2017
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 22, 2018 COD date. The primary critical path is through the Waste, Potable, Feedwater, and Closed Cooling Water Systems. The secondary critical path is...
Sep
19
2017
PSEG Keys Energy Center LLC and SNC-Lavalin recently joined Prince George’s County Executive Rushern Baker and the Business Resource Coalition (BRC) for an afternoon of networking, and sharing of valuable resource information. The BRC offers managerial, technical and financial assistance to local businesses.
Over 50 businesses participated and learned how...
Sep
01
2017
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 4, 2018 COD date. The Primary Critical Path remains the completion of the STG electrical, cable pulls, terminations, commissioning 125VDC, and back feeding power...
Aug
18
2017
SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC.
DCS Powered Up.
East View (July 23rd).
Station Battery Installation.
PSEG IT Rack Installation.
To view pics of our progress click here.