PSEG Keys Energy Center LLC Community Briefing With Brandywine North Keys Civic Association

PSEG Keys Energy Center LLC Project Compliance Officer Eben Smith recently gave a briefing to Brandywine North Keys Civic Association regarding recent updates with the project. During the discussion, he updated the civic association members on a variety of topics ranging from SNC-Lavalin construction progress, to community benefits, to local...

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of February 1, 2018)

The project remains under budget and on schedule. The Primary Critical Path remains the commissioning of HRSGs 11 & 12, low-pressure feedwater, high-pressure feedwater, intermediate pressure feedwater, and fuel gas systems to support CTG first fire. First Fire drives Steam Blows & Pipe Restoration. The Component...