(Brandywine, Maryland – January 22, 2018) – PSEG Keys Energy Center in Brandywine, Maryland, currently under construction, is urging area residents to be alert to scams in the area. In the most recent scam, a mailer recently was sent bearing the Keys Energy Center name and address as the...
Jan
19
2018
PSEG will be pressurizing the gas transmission pipeline on Sunday morning, January 28th, between approximately 8:00 and 9:00am.
During this evolution, there will be audible noise at both the Keys Project Site in Brandywine and at the Dominion M&R Station on Woodville Road in Charles County.
The noise is due...
Jan
02
2018
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The Primary Critical Path remains the commissioning of the condensate, HRSG11, low-pressure feedwater, high-pressure feedwater, intermediate pressure feedwater, and fuel gas systems to support CTG 11 first fire. First...