PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of November 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018.  PSEG Project team and Operation staff continue performing piping installation and task complete verifications to support SNC scheduling and work prioritization leading to system completions.

The Primary Critical Path remains through the Waste Water, Potable, and Closed Cooling Water systems as well as the Instrument Air system.  The Secondary Critical Path is through the Demin and Condensate Systems.  Generator Step-Up and Station Auxiliary Transformers 11& 12 remain energized with High and Medium Voltage MCC’s energized.

All UPS systems are also energized.  Seven of 14 HRSG Hydrostatic Tests have been completed.  The CTG 11 Lube Oil Flush is in progress.  Current site manpower is 740 with 170 on night shift.