PSEG Keys Energy Center LLC and SNC-Lavalin recently joined Prince George’s County Executive Rushern Baker and the Business Resource Coalition (BRC) for an afternoon of networking, and sharing of valuable resource information. The BRC offers managerial, technical and financial assistance to local businesses. Over 50 businesses participated and learned how...

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of September 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 4, 2018 COD date. The Primary Critical Path remains the completion of the STG electrical, cable pulls, terminations, commissioning 125VDC, and back feeding power...