PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of August 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018.  The Primary Critical Path runs through activities leading up to backfeed, energization of #12 Station Power Transformer and commissioning.  The STG has 10 days of float due to schedule optimization and the addition of Siemens Supervision.  Tray / Conduit installation and Cable Pulls remain in progress ahead of plan.  BHI continues High Pressure pipe welding on the HRSGs.  NSE/Milco continues Balance of Plant Piping installation.  The Admin Building/Control Room are nearing completion for occupancy, with the Control Room Operator Consoles and Digital Control Systems being installed.  The Total site manpower is 947 with 182 on night shift.