Aug
18
2017
SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC.
DCS Powered Up.
East View (July 23rd).
Station Battery Installation.
PSEG IT Rack Installation.
To view pics of our progress click here.
Aug
01
2017
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The Primary Critical Path runs through activities leading up to backfeed, energization of #12 Station Power Transformer and commissioning. The STG has 10 days of float due to schedule optimization and the...