PSEG Keys Energy Center Participates In PGC SDDD’s County Connections Event

PSEG Keys Energy Center recently participated in Prince George’s County Supplier Development & Diversity Division (SDDD) County Connections event. The kickoff event was co-hosted by Council Chair Derrick Davis (District 6) and provided businesses with the opportunity to meet and receive information essential to local and regional business growth. Attendees...

SNC-Lavalin Construction Progress Pictures Of The PSEG Keys Energy Center LLC (7/15/17)

SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC. Latest Site Aerial (6/25/17). HRSG 11 Stack Topped and Silencer Support Steel Installation. Condensate Pump Motor Installation. HRSG 11 Stack Topped and Silencer Support Steel Installation. To view pics of our progress click here.

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of July 3, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April 8, 2018 COD date. The STG has become the Primary Critical Path with preparations for setting of the LP Inner Casing in progress. Ready...