Prince George's County Councilman Mel Franklin and Maryland State Delegate Susie Proctor recently joined PSEG Keys Energy Center to celebrate the graduation of the participants of the Keys Energy Program, Councilman Franklin lauded the participants for their achievements while Delegate Proctor recognized the participants with a citation.  Both officials spoke...

PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of May 1, 2017)

The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018 and a target of April 1, 2018. The Steam Turbine Generator remains the primary critical path with STG Electrical the second path. Load testing of the Turbine Building Overhead Crane is scheduled...