PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of February 1, 2017)

The critical path remains through the heat recovery steam generators (HRSG) and the Steam Turbine.  Construction of the #11 and #12 HRSGs continues with installation of side panels and floor and roof sections.  The high pressure steam drums have been set on top of the HRSGs.  The Steam Turbine / Generator will be set on their foundations by February 3rd.  Erection of building steel continues.  Piping and electrical for the CT/CTG11 & 12 support modules (lube oil, compressor and electrical) continues.   Erection of the ACC continues with 24 of 36 cells erected to the fan level. Installation of the new PEPCO substation and the plant switchyard remain on schedule.