PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of November 1, 2016)
Work at the plant site continues with the critical path being the completion of major equipment pedestals and setting of HRSG bundles. All major equipment foundations have been completed. The project achieved a major milestone this month with the commencement of ACC Structural Steel going up. The first HRSG Bundles will be set the week of November 7th. Erection of the Demin and Fire Water Tanks continues. The off-site 8 mile gas pipeline has been completed and placed under a nitrogen purge until gas is needed at the site. Construction of the new PEPCO Cheltenham Substation and Plant Switchyard also continues.