SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC. Work at the plant site continues with the critical path being the installation of building foundations. The first major foundation, for the #11 Combustion Turbine-Generator (CTG), was poured on September 24th. The #11 Heat Recovery...
Oct
17
2016
Prince George's County Council Chair Derrick Davis recently visited the students of the PSEG Energy Career Program.
During the visit, he learned about the program and spoke with students about taking advantage of the opportunity to have a potential career in the energy industry. He also talked with students about how the program...
Oct
10
2016
Please be advised that there will be overnight heavy hauling to and from the PSEG Keys Energy Center LLC construction site commencing Monday, October 10, 2016 to Thursday, October 13, 2016. The hauling will from Ice Plant Road to the site on North Keys Road.
The heavy haul will occur...
Oct
05
2016
Work at the plant site continues with the critical path being the installation of building foundations. The first major foundation, for the #11 Combustion Turbine-Generator (CTG), was poured on September 24th. The #11 Heat Recovery Steam Generator (HRSG) was poured on October 1st, and the foundation for the Steam...