SNC-Lavalin will be conducting a concrete pour on the PSEK Keys Energy Center construction site early Saturday morning commencing between 1:30am and 2:00am on 9/24/16.
The concrete pour cannot stop once started and will need the largest window of time with the least amount of traffic on the...
Sep
15
2016
PSEG Keys Energy Center and SNC-Lavalin recently participated in the Brandywine North Keys Civic Association Community Picnic at the North Keys Community Park. The free event invited the community out for a day of fun for the entire family.
The picnic is an effort to bring the community together with businesses...
Sep
08
2016
PSEG Keys Energy Center LLC is pleased to announce our new text alert system that sends emergency alerts, notifications, and updates to your mobile devices.
Whether it be emergencies, road closure updates, or getting advanced notice of tests and other other activities that could create noise or other observations,...
Sep
01
2016
Work at the plant site continues with the critical path activities being the installation of power block underground electrical and piping in advance of foundation work. The footer foundations for the Demin and Fire Water Tanks have been poured. Construction of the new PEPCO Cheltenham Substation is well underway...