Aug
30
2016
Otis Eastern Services continues to make progress on the 8-mile natural gas pipeline for the PSEG Keys Energy Center LLC. They are progressing on schedule and will be nearing completion soon. See pics of the pipeline construction progress below.
Grading, seeding, and mulching completed on the pipeline right-of-way.
Grass starting to...
Aug
23
2016
PSEG Keys Energy Center LLC, SNC-Lavalin and Otis Eastern Services in conjunction with the PGC Supplier Development & Diversity Division (SDDD) recently invited all interested local and minority businesses to meet with our project and procurement representatives at our PSEG Keys Energy Center LLC Vendor Day.
During the vendor appointments,...
Aug
08
2016
Current construction site conditions of PSEG Keys Energy Center Site. SNC-Lavalin, the designated engineering, procurement and construction contractor for the PSEG Keys Energy Center, continues to make progress.
Click here to see more of our progress.
Aug
01
2016
Work at the plant site continues with the installation of underground piping and electrical within the main plant excavation. Construction of the new PEPCO Cheltenham Substation on the site also commenced with the installation of the auger-cast piles for structural steel support.
The temporary site warehouse fabric structure has been...