PSEG Keys Energy Center LLC Construction Progress Pictures (7/25/16)

SNC-Lavalin continues to make progress at the PSEG Keys Energy Center LLC. Switchyard Installed Piers Keys Site. Ware House Structure Looking S Keys Site. Warehouse Big Top Errection Keys Site. Warehouse Big Top Keys Site. Switch Yard Pier Installation Keys Site. Ware House Structure Looking S Keys Site. Warehouse Big Top Errection Keys Site. CT 11 WWD...

SNC-Lavalin Implements Noise Control Plan At PSEG Keys Energy Center LLC Construction Site

In an effort to ensure certain noise levels are kept to an acceptable level at the PSEG Keys Energy construction site, SNC-Lavalin has created a noise control plan designed to reduce the impact of noise on area residents. The goal of the plan is to reduce the impact of noise...

PSEG Keys Energy Center: Construction Status Update (As Of July 1, 2016)

In June, PSEG and SNC Project Management personnel relocated from temporary off-site office to the main plant site. The plant entrance road was paved with asphalt, and installation of the temporary fabric warehouse will be completed in early July. The craft parking lot has been completed and is in...