Site construction activities at the plant site on North Keys Road continue to increase. Installation of on-site underground utilities and excavations for the power plant foundations are in progress. The temporary on-site warehouse will be erected in June. The temporary Project Management Offices and temporary trailers for restrooms, changing rooms, and training have been erected.

Work to install the off-site water & sewer lines will commence on June 20th by Ferreira Construction Company. A letter was sent to homes and business in the work area regarding road closures necessary for this work.

Installation of the off-site gas piping has commenced at the southern end in Charles County.