SNC-Lavalin Project Milestones (4/12/16)

SNC-Lavalin Project Milestones:

November 2015
• SLCI focused on Engineering and Procurement to support the detailed design activities and the ordering of major equipment and materials.

• Construction team continued to support the site grading.

• Construction continued to monitor the environmental mitigation efforts to stay in compliance with all
permit requirements.

• Construction completed building of the Site Surcharge Pile.

December 2015

• SLCI continued to focus on Detailed Design and the procurement of major equipment and materials.

• Construction team continued to support the site grading.

• Construction continued to monitor the environmental mitigation efforts to stay in compliance with all permit requirements.

January 2016

• SLCI continued to focus on Detailed Design and the procurement of major equipment and materials.

• Construction team continued to support the site grading.

• Construction continued to monitor the environmental mitigation efforts to stay in compliance with all permit requirements.

• Construction completed Site Surcharging and began Surcharge pile removal.