PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of March 1, 2018)
The project remains under budget and on schedule to meet PJM Commitments. The Primary Critical Path is through the commissioning and loop checks for the...
PSEG Keys Energy Center LLC Community Briefing With Brandywine North Keys Civic Association
PSEG Keys Energy Center LLC Project Compliance Officer Eben Smith recently gave a briefing to Brandywine North Keys Civic Association regarding recent updates with the...
PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of February 1, 2018)
The project remains under budget and on schedule. The Primary Critical Path remains the commissioning of HRSGs 11 & 12, low-pressure feedwater, high-pressure feedwater, intermediate...
PSEG Keys Energy Center Alerts Residents Of Local Mail Scam
(Brandywine, Maryland – January 22, 2018) – PSEG Keys Energy Center in Brandywine, Maryland, currently under construction, is urging area residents to be alert to...
Special Alert: PSEG Will Be PSEG Pressurizing The Gas Transmission Pipeline On 1/28/18
PSEG will be pressurizing the gas transmission pipeline on Sunday morning, January 28th, between approximately 8:00 and 9:00am. During this evolution, there will be audible...
PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of January 1, 2018)
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The Primary Critical Path remains the commissioning of...
PSEG Keys Energy Center And SNC-Lavalin Honored By PGC SDDD For Supplier Diversity Efforts
Prince George’s County Supplier Development & Diversity Division (SDDD) in the Office of Central Services selected PSEG Keys Energy Center And SNC-Lavalin as an honoree...
PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of December 1, 2017)
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The Primary Critical Path remains the commissioning of...
PSEG Keys Energy Center LLC Makes Final $1 Million Payment Towards Construction Of A New Southern Area Aquatic And Recreation Complex
In keeping with the commitments of our Community Foundation Agreement, PSEG Keys Energy Center LLC recently made it’s final $1 million payment towards the construction...
PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of November 1, 2017)
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018.  PSEG Project team and Operation staff continue performing...
SNC-Lavalin Construction Progress Pictures Of The PSEG Keys Energy Center LLC (10/16/17)
SNC-Lavalin continues to make progress on construction of the PSEG Keys Energy Center LLC. October Aerial: ACC Steam Distribution Manifold Painting: CTG Air Inlet Filter...
PSEG KEYS ENERGY CENTER: CONSTRUCTION STATUS UPDATE (as of October 1, 2017)
The project remains on budget and schedule with a Guaranteed Substantial Completion Date of May 1, 2018. The current Critical Path Schedule has an April...